Project Introduction
Design, Fabrication And Installation Of 45000 Sqm. Steel Structure Standard Manufacture Units
Built-up Area: 45000 sqm.
Structure steel Design, Fabrication And Installation
This is a demonstration project for national cooperation between China and UAE, we finished the structure design as per U.S. design codes by using Chinese standard materials and it was approved successfully, then finished the fabrication in a short time. Most importantly, the project is carried out mainly during the COVID-19, but in addition to ensuring our safety, we completed the Installation of the frame of one of the factory buildings in 30 days, including waiting for material and equipments. By the way, the temperature during these days is 30-46 degree centigrade (86-114.8 Fahrenheit degree).